What is a fundamental disadvantage of using precast concrete?

Prepare for the ExAC Section 3 exam with our comprehensive materials. Utilize flashcards and multiple choice questions, complete with hints and detailed explanations, to ensure you're well-prepared for your architectural certification! Ready to ace your exam?

The fundamental disadvantage of using precast concrete primarily revolves around the heavy transportation requirements. Precast concrete elements are manufactured in a factory setting and then transported to the construction site. This process often involves considerable logistical challenges, including the need for specialized vehicles to handle the weight of the precast elements. Transporting these large and heavy components can also lead to increased costs and necessitate careful planning to ensure they arrive at the job site safely and on schedule.

In comparison, while the other options may present issues in specific contexts—such as higher costs, thermal properties, or the process of pouring concrete on-site—they do not encapsulate the broad logistical and economic challenges associated with the transportation of precast elements as completely as this option does. The heavy transportation requirements can complicate project timelines and budgets, making it a notable disadvantage of precast concrete use in construction.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy